Airtech
Published

Faster...is better

Ten months….that’s a lot of time, in my book. Why do public works agencies tolerate such drawn-out projects using traditional materials, when composites are faster, more efficient and more durable?

Share

Ten months….that’s a lot of time, in my book. I have been casually observing the replacement of a bridge near my home in Colorado, a bridge over a tiny stream on a road that leads to a park. The existing bridge was demolished, and new abutments built, followed by placement of six steel girders, with several cranes, then a poured concrete deck. Once the deck was fully cured (under blankets and tarps), work progressed slowly on the parapets and access aprons, and finally, this week, an asphalt cover was placed. It took nearly one year to build a very small, two-lane bridge with a span of approximately 30 feet.

Well, it may be that the project posed some difficult challenges that took extra time, and the Colorado winter certainly didn’t help speed things along. But I couldn’t help but think, every time I passed the construction site, about the many stories we’ve published over the years about composite material solutions for bridges. The main point of those stories has always been that the bridge is built by a composites fabricator, off-site, and delivered in a modular fashion, allowing installation to be accomplished in days, or even, hours. The on-site labor savings is significant, heavy cranes aren’t required, the road opens sooner….surely the time and effort savings of that scenario outweigh the higher material cost — yes?

Unfortunately, the answer seems to be “no” more often than not. The tried-and-true methods of cured-in-place concrete persist in many departments of transportation, even though the Federal Highway Administration (FHWA) has been pushing, for four years now, accelerated bridge construction (ABC) initiatives under the name Every Day Counts (EDC). EDC is a collaborative effort that involves the FHWA, the American Association of State Highway and Transportation Officials (AASHTO), state departments of transportation (DOTs), local agencies, and industry, and is aimed at reducing overall project delivery time and impacts from onsite construction. Among the many ABC alternatives (which include better planning, fee structure changes and greater right-of-way and utility flexibilities), is a construction concept called Prefabricated Bridge Elements and Systems, or PBES.

PBES include not only the structural components of a bridge that can be built at offsite locations, like a composite deck, but also components that can be constructed without traffic disruption adjacent to construction sites, given sufficient room and access. Examples include full-depth precast concrete deck panels, steel grid decks, aluminum deck panels, modular beams with decks, full-width beams, prefabricated truss spans, precast segmental spans, pier elements, abutment and wall solutions and miscellaneous items, such as prefabricated parapets and approach slabs. They also could include preassembled composite superstructures or complete bridges.

Ben Beerman of the FHWA wrote about PBES for CompositesWorld in 2012 (http://www.compositesworld.com/columns/prefabricated-bridge-elements-and-systems-an-opportunity-for-composites), but even the FHWA itself is struggling with convincing entities to adopt the concept. “PBES often cost more at the bid stage, and they require planning and coordination,” says Scott Reeve, president of Composite Advantage (Dayton, Ohio, USA), a composite bridge design and build firm. “But, they have less potential for change orders that inflate the final costs of long projects.” He points to an example of how PBES can accelerate a project significantly: the Mitchell Gulch bridge construction project, ironically, located in the State of Colorado. A deteriorated timber structure on a secondary road in Douglas County, Colorado needed replacement, and CDOT and designer Wilson and Company (Denver, Colo., USA) seized the opportunity to use precast concrete modules, including precast concrete deck girders that acted as the actual bridge deck. After significant upfront planning, advance part production and preliminary site work that didn’t disrupt traffic, the old bridge was swiftly demolished starting at 7:00 pm on a Friday night (with demolition completed in 5 hours). The completed precast elements were then put in place in a complex choreography, and by Sunday afternoon of the same weekend, paving was underway (here’s a link to that case study story on Mitchell Gulch, on the FHWA Web site:  https://www.fhwa.dot.gov/hfl/co2story.pdf).

That’s 2 days and change, compared to 10 months for my bridge. While the Mitchell Gulch example used precast concrete, Reeve points out that if accelerated bridge methods using PBES can be advanced successfully, “It’s a change for the better. The composites industry will get at least part of that work, as more DOTs adopt this approach.” Our aging infrastructure could really benefit from a faster, and better, refresh.

Coast-Line Intl
Airtech
Zone 5 CLEAVER
CAMX 2024
Composites product design
HEATCON Composite Systems
CompositesWorld
Release agents and process chemical specialties
NewStar Adhesives - Nautical Adhesives
CompositesWorld
Advert for lightweight carrier veils used in aero
Airtech

Related Content

Sustainability

CirculinQ: Glass fiber, recycled plastic turn paving into climate solutions

Durable, modular paving system from recycled composite filters, collects, infiltrates stormwater to reduce flooding and recharge local aquifers.

Read More

National manufacturing center for FRP infrastructure opened in Australia

Four-year program between Sustainable Infrastructure Systems, InfraCore leads to internationally certified composite bridge, jetty, wharf, pontoon and lock gate manufacture, research in recycled materials.  

Read More
Infrastructure

Composites end markets: Infrastructure and construction (2024)

Composites are increasingly used in applications like building facades, bridges, utility poles, wastewater treatment pipes, repair solutions and more.

Read More
Infrastructure

Creative Composites Group integrates Ohio, Maine molding manufacturing capabilities

Flexible approach will provide added capacity to speed up project delivery, meet increased customer demands.  

Read More

Read Next

Plant Tours

Plant tour: Teijin Carbon America Inc., Greenwood, S.C., U.S.

In 2018, Teijin broke ground on a facility that is reportedly the largest capacity carbon fiber line currently in existence. The line has been fully functional for nearly two years and has plenty of room for expansion.

Read More
Past, Present and Future

The next-generation single-aisle: Implications for the composites industry

While the world continues to wait for new single-aisle program announcements from Airbus and Boeing, it’s clear composites will play a role in their fabrication. But in what ways, and what capacity?

Read More
Additive Manufacturing

Combining multifunctional thermoplastic composites, additive manufacturing for next-gen airframe structures

The DOMMINIO project combines AFP with 3D printed gyroid cores, embedded SHM sensors and smart materials for induction-driven disassembly of parts at end of life.

Read More
Airtech International Inc.